PE 4590 - FS 2019 Final Economics Project -Offshore Field Development- West Africa

Assignment Writing Help

This assignment question was recently posted by one of our customers and shared with our professional writers. If you are looking for assignment help on this topic or similar topic, click on ORDER NOW button to submit your details. Once we have your order details, your assignment will be assigned to one of our best writers, who will then proceed to write your paper and deliver it within your specified deadline. Thank you for choosing us today!

PE 4590 - FS 2019 Final Economics Project -Offshore Field Development- West Africa

PE 4590 – FS 2019

Final Economics Project -Offshore Field Development- West Africa

 

Your company has entered into a production sharing agreement (PSA) in the blocks #10 and #24 immediately adjacent to Angola, West Africa, March 2018. The agreement expire in the year 2022 if there is no commercial production demonstrated or planned by that time, but will cover a period of 20 years from the time any development plans are agreed. Figure 1 shows the locations of blocks 10 and 24.

 

Figure 1.  Location of Lease Blocks Offshore Angloa

 

An exploratory, vertical well was drilled in Block #10 during November, 2018. This well tested with an AOF of 2500 STB/day from approximately 180 ft of net pay in the Pliocene in the main structure. A subsequent vertical well was drilled west in the main structure but in Block 24, proving the northern portion of the main structure as productive. However, seismic indicates there could be a downthrown fault across the field (shown with the dotted line).  There is a 60% of this faulting and if this exists, then wells drilled on the downthrown side will be wet and will not be oil productive.  

 

Two smaller structures can be seen on seismic, but haven’t yet been drilled.  It is estimated there is a 50% chance of these wells also being productive in the Pliocene.

 

Water depths vary from 500 ft in the eastern portion of block #10 to slightly over 2000 ft in the western portions of Block #24. The average water depth at the initial drillsite for the first exploratory well was 650 ft.

 

It is estimated that each well will produce with an initial rate of 2400 bopd, declining at 7% per year. The abandonment rate for each well is expected to be 50 bopd. Each well will drain an area of approximately 1 sq mile. The oil produced from the field is light (31 deg API). The oil has a low producing GOR of 500 scf/stb. This GOR is expected to remain relatively constant. You must provide a use for the gas or re-inject it into the reservoir. (No flaring is allowed now offshore Angloa.)

 

Angola is an area of high activity and you should consider that as you formulate your development plan.

 

There is currently only one refinery in Angola – the Luanda Refinery with a capacity of ~65,000 bopd. ENI promoted an international public tender and awarded a contract to expand the gasoline processing capacity of this refinery. A second national refinery project is, planned for the city of Lobito, is currently on hold but will likely be constructed in 2 more years.  https://www.export.gov/article?id=Angola-Oil-and-Gas  Google the location of Luanda refiner, the city of Logito and use the scale on Figure 1 to estimate how far this refinery and the site of the proposed refinery are from your leaseblocks.

 

You may use any resources and appropriate assumptions that you like to complete this project, but all resources should be copied, attached and correctly cited.  For an oil price, you should start with current oil prices and use the World Bank average crude oil projection (Figure 2):

 

 

Figure 2.  World Bank Average Crude Oil Price Projections found at

https://knoema.com/yxptpab/crude-oil-price-forecast-2019-2020-and-long-term-to-2030

 

 

 

MAIN PROJECT TASKS

 

  1. Define the key financial terms (cost recovery, tax, royalty, etc) of the production sharing contract you negotiated with Angola for this project.

 

  1. Determine the risk weighted reserves associated with these structures.

 

  1. Assume the small structure in Block 10 is successful, there is no fault in the main structure, but the small structure to the north is dry. Develop a field development plan for the two productive structures. 

 

Some key things to decide:  If each well drains 1 sq mile, how many wells are required?  How much drilling time?  What type of main production facility will you use?  How far can a directional well reach from that main facility?  Do you need more than one production facility to drain the structure?  What is the timing for all facilities/drilling etc?  How will you transport your oil to shore and process it?

 

Note: If you are drilling many wells from a single production facility you will likely use many deviated wells. KOP should be 2000 ft, and the maximum deviation is 60deg. Buildup rate = l deg/100 ft.  Pliocene reservoir depth averages 8000 ft (below mud line). Assume a common KOP for all wells and then find the maximum lateral reach given this drilling plan.  You can choose to use satellite subsea templates and vertical wells also.

 

  1. Make a copy of the structure map and show the locations of main production facilities, well reach from those facilities (for any deviated wells) and the locations of all wells (including future injection wells).

 

  1. Determine the project schedule showing timing for all capital expenses, drilling costs, etc. Show costs on an annual basis.  Prepare a Gantt chart of the major tasks and show their timing by year.  Engineering design for the project should begin in January, 2019.   Allocation of annual capital and operating expenses much match the activities shown on the Gantt chart.

 

  1. Develop a cash flow for the project using the terms of your PSA for 20 years.

 

  1. What is the net present value of this project for your company?

 

  1. Prepare an Executive Summary of the work which details any assumptions made in the evaluation. Attach any references used (not required but if you found information from a source, then cite that source in your Executive Summary).    Prepare a cover letter for the project which gives a 1 paragraph summary of the findings, costs, any key economic indicators you feel are important and a recommendation of whether to sign the PSA.

 

 

 

 

 

 

 

 

 

Expected Development Times for Various Project Tasks

 

 

TASK                                                                          DURATION

 

Preliminary engineering studies                                               3 months

Contractors bids and bid award                                               1 month

Detailed engineering studies                                        5 months

 

Platform drilling and completion                                 2 months/well

Subsea drilling and completion                                                2.5 months/well

 

Steel jacket design and fabrication (up to 1000 ft water)         12 months

Steel jacket design and fabrication (over 1000 ft water)          15 months

Subsea template design and fabrication                                   9 months

 

Steel jacket installation            and commissioning                  0.5 month

Template installation and commissioning                    0.25 month

 

In-field subsea flowline fabrication/install                   3 weeks/mile

Pipeline to shore (oil or gas) fabricate and install                     12 months                                           

 

 

 

Drilling and Production Facilities Costs

Steel jacket & topsides for up to 1000 ft water depth              $75MM

Steel jacket & topsides for over 1000 ft water depth               $125MM                                             

 

Export pipeline to shore                                                                       $1MM/mile

In-field flowlines and umbilicals                                                         $500M/mile

 

Platform drilling and completion                                             $20MM/well

Subsea drilling and completion                                                            $25MM/well

Subsea template cost                                                                $20MM

Subsea production manifold                                                    $5MM

 

Controls package at central facility for subsea wells                $5MM/template OR

                                                                                                $500M for a single subsea well                                                                      

 

Operating Costs

Annual general operating cost                                                  1% of production facilities CAPEX  (exclude drilling and completion)

 

Assume every well requires workover once every 6 years      $5MM/well – once every 6 years.

 

 

 

Other Operating Costs

Throughput cost if using another companies export line                      $0.65/stb transported

(You must demonstrate where that line is)

 

Academic Writing Help

All writing formats, 24/7 customer support via live chat, email or phone number, and timely delivery guaranteed.

Are you looking for homework writing help? Click on Order Now button below to Submit your assignment details.

Homework Writing Help
We Can Help you with this Assignment right now!

Are you looking for homework writing help on this topic? This question was posted by one of our client seeking homework help.  If you are therefore looking for an assignment to submit, then click on ORDER NOW button or contact us today. Our Professional Writers will be glad to write your paper from scratch, and delivered within your deadline. Perfect choice for your excellent grades! www.globalcompose.com.

 

We ensure that assignment instructions are followed, the paper is written from scratch. If you are not satisfied by our service, you can either request for refund or unlimited revisions for your order at absolutely no extra pay. Once the writer has completed your paper, the editors check your paper for any grammar/formatting/plagiarism mistakes, then the final paper is sent to your email.

Privacy| Confidentiality

We do not share your personal information with any company or person. We have also ensured that the ordering process is secure; you can check the security feature in the browser. For confidentiality purposes, all papers are sent to your personal email. If you have any questions, contact us any time via email, live chat or our phone number.

Our Clients Testimonials

  • I appreciate help on the assignment. It was hard for me but am good to go now

    Impact of pollution on Environment
  • Am happy now having completed the very difficult assignment

    Creative Message Strategies
  • Your writer did a fine job on the revisions. The paper is now ok

    Ethics: Theory and Practice
  • The paper was so involving but am happy it is done. Will reach you with more assignments

    Title: Privatization in or of America
  • I expected perfection in terms of grammar and I am happy. Lecturer is always on our head but was pleased with my paper. Once again, thanks a lot

    Title: Bundaberg Inquiry
  • The paper looks perfect now, thank to the writer

    Health Care Systems
  • You helped me complete several other tasks as you handled paper. wonna thank you

    Critique Paper on Political Change

Related Articles

Analyze the Nursing Roles in providing Comprehensive care in a Variety of Community Health Settings

Community Settings This week’s graded topics relate to the following Course Outcomes (COs). CO3: Plan prevention and population-focused interventions for vulnerable populations using professional clinical judgment and evidence-based practice. (POs...
Read More

Case Study Assignment on Ethical Issues in Asia-Pacific business

Case study assignment on Ethical Issues in Asia-Pacific business For this assignment, students will write a case study report in 2,000 words based on a case identified with circumstance or...
Read More

Sample Report Paper on The proposed reward system and strategy for the big city university

A good reward system should motivate workers. It should also attract and retain the same workers. On the contrary, a bad reward system does not do either of these things....
Read More

Management of PCOS through Homoeopathy-A case report

Introduction PCOS is the acronym for Polycystic Ovarian Syndrome. It is the most common endocrine disorder of women in their reproductive period manifested by irregular menstrual cycles and polycystic ovaries,...
Read More

Get more from us…

Would you like this sample paper to be sent to your email or would you like to receive weekly articles on how to write your assignments? You can simply send us your request on how to write your paper and we will email you a free guide within 24-36 hours. Kindly subscribe below!

Email Address: support@globalcompose.com